Vote
Company procedures often say "set according to UKC policy". How are the numbers worked out for a passage?
asked 2 d agoAdmin
Deck & Navigation › Bridge equipment (ECDIS, radar, GMDSS)
Company procedures often say "set according to UKC policy". How are the numbers worked out for a passage?
Start from the company's under-keel clearance (UKC) policy. A common approach: safety contour = draught + required UKC + an allowance for squat, minus the height of tide only if your procedure allows using tide.
If that value is not in the chart, ECDIS uses the next deeper contour available. Set the safety depth to the same value so that shallower soundings are highlighted.
Write the values in the passage plan for each leg, because they change with draught and tide.